10 July 04: While work continues on the roof and the last of the blockwork to the rear extension is underway, a lot of the 'first fix' (the main pipes) for the plumbing are now in
place
11th July 04: The detailing around the round window at the top of the front wall and the new rooflights to the side annex are in
19th July 04: The plasterers have just started work. Either side of the window the metal 'beads' are in place ready for render to be added to the front wall.
24th July 04: The plasterers have completed the first coat of render to the front wall, and the slating of the side annex is almost halfway
29th July 04: Some areas of render are complete and work on plasterboarding the side hall ceiling is under way