2nd June 2004: Main walls for the side annex are now 2m high and the brick details are starting to show.
10th June 2004: Main walls for the side annex are almost full height ready for the roof to start next week
17th June 2004: The second half-tonne truss being craned into position.
27th June 2004: Internal walls under way, and the old church office now stripped out